Transforming visitor toilets for London’s iconic Natural History Museum

As Principal Contractor, Mitie fully refurbished the visitor toilets at one of London's most iconic museums within four months.

The entrance hall at London's Natural History Museum
AI Summary
  • The Natural History Museum completed its toilet refurbishment on time in 2025 despite challenges.
  • The museum welcomed a record-breaking 7.1 million visitors in 2025, making it the UK's most visited attraction.
  • Construction was completed with minimal disruption to visitors, maintaining public access and controlling noise and dust.
  • Mitie used night shifts to overcome supply chain delays and keep the project on schedule.
  • The refurbishment improved comfort, accessibility, and visitor experience with modern sanitaryware and facilities.

Generated with AI

7.1m

visitors in 2025

4-month

programme completed on time

Zero

disruption to daytime visitor experience

Overview of the challenge

The Natural History Museum needed to transform their ageing toilet facilities into modern, accessible spaces that matched visitor expectations – without compromising day-to-day operations.

The Museum welcomed a record-breaking 7.1m visitors in 2025, making it the UK’s most visited attraction that year. But delivering construction work in a live, high-footfall heritage environment brought added complexity. Public access had to be maintained at all times, with tight controls on noise, dust and disruption. Logistics were equally challenging, with deliveries restricted to specific hours and works taking place in sensitive areas of the building.

The programme also faced supply chain delays, particularly around key equipment, putting pressure on sequencing and timelines. With a fixed four-month deadline, the project demanded careful planning, flexibility and close collaboration to keep everything moving without impacting the visitor experience.

Mitie colleague at The Natural History Museum

Our approach

Mitie took full responsibility as Principal Contractor, leading the planning, coordination, management and delivery of the refurbishment works.

A carefully phased programme allowed construction to progress while the Museum remained fully operational. When supply chain delays threatened the schedule, the team adapted quickly, introducing targeted night shifts to maintain momentum. This enabled critical activities to continue without affecting visitors or daytime operations.

The works included a full refurbishment of the North Hall toilets and the Waterhouse East basement toilet facilities, delivering new sanitaryware, mechanical and electrical improvements, enhanced finishes and improved accessibility throughout.

Strong stakeholder communication, strict health and safety controls and high standards of cleanliness ensured the environment remained safe and welcoming throughout the project.

The results

Visitor toilets at The Natural History Museum
Bathroom sink taps in London's Natural History Museum

The Museum now has modern, high-quality facilities that significantly improve comfort, accessibility and the overall visitor experience.

Despite programme pressures, the works were delivered on time, safely and with minimal disruption. As a result, the outcome has demonstrated how flexible planning and proactive delivery can keep complex projects on track in live public environments.

Why choose Mitie?

Plan, deliver and optimise capital projects across the built environment. Whether it’s a major engineering programme or a targeted upgrade, our role as a principal contractor covers everything from strategy and design through to execution and optimisation.  

Stained glass window at London's Natural History Museum

Our services

  • Energy and power  
  • Built environment  
  • Workplace experience